Project Overview
Lime kiln emergency repair and refractory replacement for a major construction materials producer. The project was completed under tight time constraints.
Scope of Work
- Emergency repair: 48 hours
- Complete refractory replacement
- Kiln diameter: 3.8 meters
- Installation time: 10 days
Technical Solution
Rapid deployment of pre-engineered refractory components and expert installation team.
Outcomes
- Furnace back online: 12 days (vs. 30 days estimated)
- Production recovery: 100% within 3 weeks
- Cost savings: $150,000
- Zero safety incidents